LADWP Sunset Plaza Pipe Project Update

Posted on 10/20/20

Bel Air-Beverly Crest Neighborhood Council

We received this update from LADWP:

  • PROJECT STATUS UPDATE
     
  • Overall Status-   The pipe has been installed within Phase 2 and our crews are currently transferring services to the new pipe. Once Phase 2 is complete, Sunset Plaza Dr will be open for vehicular travel and Phase 3 will commence. LADOT Traffic Officers (TCO’s) are currently deployed at the intersection of Hollywood Blvd and Queens Rd to help mitigate any traffic backups along the detour route.
  • Upcoming Work-   Crews have laid out trench excavation on Viewsite Dr to prepare for Phase 3. We expect to start Phase 3 by first week of November (November 2 Target Date).
  • Street Closures/Parking-   Phase 2 will continue to have Sunset Plaza closed from Haslam Terrace  to Hollywood Blvd. There is currently no complete access on Sunset Plaza Drive. Once Phase 2 is complete, Sunset Plaza Dr will be open for vehicular travel. However, residents who live between Haslam Terrace to Rising Glen Rd may exit Sunset Plaza South of the current work area. Once Phase 3 commences, Parking will be restricted on Viewsite Dr and residents will need to park outside of the closure.
  • Work Hours- Monday through Friday, 9AM to 6PM. Residents will be notified in advance if the work schedule changes at any time.
 

© Bel Air-Beverly Crest Neighborhood Council. All rights reserved.

Accessibility       Privacy Policy

Join Our Mailing List

Web Design by The Web Corner

© Bel Air-Beverly Crest Neighborhood Council.
All rights reserved.
Accessibility       Privacy Policy

Join Our Mailing List